Housing R/C delay night shift, Door outer jigs rotation delay… 669L RR substrate NG no inform T/F so file wasted. Due to poor communication
May need panic switch
Jig repair need spot weld and one more person
Inspection T/F: 4.14%
Robot down all night last night due to stand would not pop up
วันจันทร์ที่ 15 กันยายน พ.ศ. 2551
วันอาทิตย์ที่ 14 กันยายน พ.ศ. 2551
PCI Meeting Sep 15 2008
3E00 no need DI water, not enough DI water to support all Porducts, Pe Jade Suggest to close down bottom nozzles , RO water before 3 tanks about 12 but out 40
No Standard for T/C antistatic airblow,
Antistatic bar start using Fri 12, continune air blow
Rebase parts from F2 quality improved a lot...
Robot shock replacment on Robot 2 on Sat.
วันพฤหัสบดีที่ 11 กันยายน พ.ศ. 2551
Sep 11 2008
Yesterday both Robot broke down, Robot 2 Stand not lift, Thinner not flow
Robot 1 older pins bended, exhurt not working
Mount Yamaha delay, X11J day delay 39 mins
Yamaha 18 mins, 669L plan mistake
Insp T/F 4.61 % Yamaha 73pcs scratch black and white, 2nd round mostly pin hole
301 Lid FP drop due to T/F increase SQ5G convayer speed wipping chemical not complete evaporate, due to mount too slow...
Robot 1 older pins bended, exhurt not working
Mount Yamaha delay, X11J day delay 39 mins
Yamaha 18 mins, 669L plan mistake
Insp T/F 4.61 % Yamaha 73pcs scratch black and white, 2nd round mostly pin hole
301 Lid FP drop due to T/F increase SQ5G convayer speed wipping chemical not complete evaporate, due to mount too slow...
วันพุธที่ 10 กันยายน พ.ศ. 2551
Sep 11 2008
ount 3E00 delay 1 hr ++ due to spray washer pipe broke
3E00 gloss NG 50 pcs. may be paint defect'
Robot error onthe conveyer and rat bit the wire stand wouldn't pop up
3E00 order for this month reduce by 2000.
669L new Jigs no pin hold Arnrest RR and RL y adjust Primary angle to 20 degree
3E00 gloss NG 50 pcs. may be paint defect'
Robot error onthe conveyer and rat bit the wire stand wouldn't pop up
3E00 order for this month reduce by 2000.
669L new Jigs no pin hold Arnrest RR and RL y adjust Primary angle to 20 degree
วันอังคารที่ 9 กันยายน พ.ศ. 2551
Sep 10 2008
YAMAHA 43 mins + 17 mins FIle adjustmet and adjust weight balance at roller coator
X11C met. 15 mins Backing change
301L Armrest 2 mins
Total 1.21 hrs.
Insp T/F 4.09% defect mostly YAMAHA and 3E00
Insp 2 301L cup needle hole 30 pcs. may be due to Yamaha cut in the middle of Origin production (YAMAHA managment visit)
Door outer paint run
669L Armrest Orange peel
Change washing detergent for dust suit
X11C met. 15 mins Backing change
301L Armrest 2 mins
Total 1.21 hrs.
Insp T/F 4.09% defect mostly YAMAHA and 3E00
Insp 2 301L cup needle hole 30 pcs. may be due to Yamaha cut in the middle of Origin production (YAMAHA managment visit)
Door outer paint run
669L Armrest Orange peel
Change washing detergent for dust suit
วันจันทร์ที่ 8 กันยายน พ.ศ. 2551
Sep 9 2008
Yesterday many delay both shift 2 hrs+ , Yamaha defect too much stop prod to later time
Night shift rat cut the wire to robots
Yamaha still have film crack problem, c
FIlm ขาด, Scatch, ยับ and pinhole nearly same percentage...
need to change T/F condition for blue color, will continune testing with New Prod Engineers
Still got paint run 45 pcs. (Blue)
Inspect T/F Day defect 6.32%
669L armrest found plastic crack new location, and there are some barric on edge of parts
Night shift rat cut the wire to robots
Yamaha still have film crack problem, c
FIlm ขาด, Scatch, ยับ and pinhole nearly same percentage...
need to change T/F condition for blue color, will continune testing with New Prod Engineers
Still got paint run 45 pcs. (Blue)
Inspect T/F Day defect 6.32%
669L armrest found plastic crack new location, and there are some barric on edge of parts
วันอาทิตย์ที่ 7 กันยายน พ.ศ. 2551
PCI Meeting Sep 8 2008
3E00, silver defect , NO metelic dust in RO water tank,,, Normal water OK testing so far OK will test one more time today
Old sray jigs have been taking out of the line
R/C sanding dust, InT/F wipe every piece will test sticky closth wiping before spray washer...
Sat. testing found that parts are clean if continune process but if hold in the cart the dust will accumulate, test include complete cleaning of part at loading point the result are vey good up to 100% FP on No.2
Old sray jigs have been taking out of the line
R/C sanding dust, InT/F wipe every piece will test sticky closth wiping before spray washer...
Sat. testing found that parts are clean if continune process but if hold in the cart the dust will accumulate, test include complete cleaning of part at loading point the result are vey good up to 100% FP on No.2
วันพุธที่ 3 กันยายน พ.ศ. 2551
September 3 2008
X11J film roll at edges and Yamaha film not cover both cause delay, 669L not process due to paint quality...
Origin Paint still have problems but some how problem not occure on evey parts
X11J too shinny
Yamaha Insp T/F have not try repairing due to no paint will try using Film but can only do on the small pin hold.
301 Armrest customers still not accept non making so need to hold those parts with film on clip
Test SW Pe Jade version look good but a little film stressed
QA FG all will be train for T/F and Mount
Mount 11->8D, 7N = -3
T/F = -1
Origin Paint still have problems but some how problem not occure on evey parts
X11J too shinny
Yamaha Insp T/F have not try repairing due to no paint will try using Film but can only do on the small pin hold.
301 Armrest customers still not accept non making so need to hold those parts with film on clip
Test SW Pe Jade version look good but a little film stressed
QA FG all will be train for T/F and Mount
Mount 11->8D, 7N = -3
T/F = -1
วันจันทร์ที่ 1 กันยายน พ.ศ. 2551
Sep 2 2008
3E00 stop and go 44 mins delay due to film edge not sharp cut causing film unstable in water
Yamaha Night delay 1:45 hr. delay...
Many Trasfer defect at Insp T/F
3E00 oil defect 66 pcs. all in same position, on Sat also happen...
Yamaha Night delay 1:45 hr. delay...
Many Trasfer defect at Insp T/F
3E00 oil defect 66 pcs. all in same position, on Sat also happen...
วันอาทิตย์ที่ 31 สิงหาคม พ.ศ. 2551
Sept 1 2008
PCI Meeting:
3E00 silver flake defect on the parts are increasing and defect get bigger,
gas curing oven cleaning burner chamber and filter will test and check dust level both end of oven before and after turn on,
Paint filter mesh found in water in robot booth, PCI to set system visual control between New, Wash and scrap filter...
Robot report, that the check valve near CCV may be in bad condiion, Axis 1 and 2 on Robot 1 always error etc.
DI RO and Normal switch valve
R/C sanding dust in the back of parts: test dishwasher
1st and 2nd Axis alway error
3E00 silver flake defect on the parts are increasing and defect get bigger,
gas curing oven cleaning burner chamber and filter will test and check dust level both end of oven before and after turn on,
Paint filter mesh found in water in robot booth, PCI to set system visual control between New, Wash and scrap filter...
Robot report, that the check valve near CCV may be in bad condiion, Axis 1 and 2 on Robot 1 always error etc.
DI RO and Normal switch valve
R/C sanding dust in the back of parts: test dishwasher
1st and 2nd Axis alway error
วันพฤหัสบดีที่ 28 สิงหาคม พ.ศ. 2551
Aug 29 2008
Mount Day 3E00 x2 delay stop and go, Wate Temp is too high 32-33 at the begining
NIght R/C masking delay
Insp 1 5.59%(No BT) @5867 pcs. YAMAHA reject pinholes need lower dipping angle the curent angle indicator not fine enough
NIght R/C masking delay
Insp 1 5.59%(No BT) @5867 pcs. YAMAHA reject pinholes need lower dipping angle the curent angle indicator not fine enough
วันพุธที่ 27 สิงหาคม พ.ศ. 2551
Aug 28 2008
Planing yesterday 669L Granish R parts not in as plan from suppler,
Mount 3E00 10 mins delay
X11J 10 mins delay x 2
and 669L Granish R as aboved
InspT/F 2.91% defect @ 5756 pcs. input
3E00 need to put the masking cover again due to FIlm ขาด downside is when wipping part the silver on cover spill to parts.
Oil Drip in oven leave make on hangers
Yamaha Paint run problems, some color fade in pink color...
60+% first time of this month due to very little 669L processes,
pass 2 weeks night shift F/P higher than day shift may be dur to temperature and humidity
Today current plan will end 12:00 and if 3E00 came in on time will have additional 3 hrs Working time
Party adjust Air Balance in Masking room, now + but need some precise doors control
Masking room FP 71% due to less work and worker can clean masking jigs cover every 4 time painting
Mount 3E00 10 mins delay
X11J 10 mins delay x 2
and 669L Granish R as aboved
InspT/F 2.91% defect @ 5756 pcs. input
3E00 need to put the masking cover again due to FIlm ขาด downside is when wipping part the silver on cover spill to parts.
Oil Drip in oven leave make on hangers
Yamaha Paint run problems, some color fade in pink color...
60+% first time of this month due to very little 669L processes,
pass 2 weeks night shift F/P higher than day shift may be dur to temperature and humidity
Today current plan will end 12:00 and if 3E00 came in on time will have additional 3 hrs Working time
Party adjust Air Balance in Masking room, now + but need some precise doors control
Masking room FP 71% due to less work and worker can clean masking jigs cover every 4 time painting
Aug 27 2008
669L still have many problems, start using new jigs which are very heavy and the setting created much pinholes, Robots also have many problems the turntable is now nearly stop, the pump is mulfunction causing many defect
Got my Agitator order from IWATA
TKT K Pakong came to discuss 669L delivery and now we use substrate 16% scrape still can not close order
Production mount finish at 3 pm.
3E00 mold brok down today so no parts for a while
Got my Agitator order from IWATA
TKT K Pakong came to discuss 669L delivery and now we use substrate 16% scrape still can not close order
Production mount finish at 3 pm.
3E00 mold brok down today so no parts for a while
วันอาทิตย์ที่ 24 สิงหาคม พ.ศ. 2551
Aug 23 2008
To TCT mainly to talk to Justin Impac, their team have observed TCT production at night time and find out many of our know weak point such as so much talking during work, the start time of Insp 2 etc...
Production found that yesterday day shift FP not good may be due to booth efficiency drop and after end shift cleaning night shift back to normal we need better review of cleaning frequency
Production found that yesterday day shift FP not good may be due to booth efficiency drop and after end shift cleaning night shift back to normal we need better review of cleaning frequency
วันพุธที่ 20 สิงหาคม พ.ศ. 2551
Aug 21 2008
Aug 20 result
Mount total delay 1 hr. (night shift),
Insp T/F 4.92% shift B only
High Humidity in T/F room, Temp is OK
Mold for 669L 4 holes brokedown TKT send for repair ETC Friday
Many defect are related to the cleanliness of surface, it is possible that the spray washer is not effective
Mount total delay 1 hr. (night shift),
Insp T/F 4.92% shift B only
High Humidity in T/F room, Temp is OK
Mold for 669L 4 holes brokedown TKT send for repair ETC Friday
Many defect are related to the cleanliness of surface, it is possible that the spray washer is not effective
วันอังคารที่ 19 สิงหาคม พ.ศ. 2551
Aug 20 2008
Test Film Taiwan Camry design : a little too dark, othewise look ok, the PVA difficult to wash off
Removed Plastic cover on the new booth T/C room to reinstate the air balance
This morning start T/F Yamaha for Suncolor
669L Arerest 4 holds deformation problems: TKT testinjection with add weight to the 4 holes part causing the one hole to be NG,still no clear direction
วันจันทร์ที่ 18 สิงหาคม พ.ศ. 2551
Aug 18 2008
Install LCD monitor in meeting room FII, First time using HDMI cable connecting from DVI port on the computer,
IMPCT Team Kick off, Factory tour and discussion
IMPCT Team Kick off, Factory tour and discussion
Aug 19 2008
Yesterday delay by T/F 45 mins. Triangular pin come lose and keep movimg out...
Major paint run problem TOYOTA day shift
R/C parts suffer needle holds
Major paint run problem TOYOTA day shift
R/C parts suffer needle holds
Mr Yor with Lutenant form Thai Air force visit SPI Khun Choto show Air Field hanger and facilities and capability
Take them to Lunch at "ภ"
Goto Novatel to meet IMPAC to sign off MOU
วันอาทิตย์ที่ 17 สิงหาคม พ.ศ. 2551
PCI Meeting Aug 18 2008
Clearing of some unused or not use often jigs to FII finish within this month
No.2 Base pill off, testing
Door Out R/B 4th round pill off, testing
Curing Gas oven need greasing ? or modification,,,, my question before doing anything is will the system work with T/C room ???
Oven Filter change
Small Antistatic booth damper cnnect to R/C booth so Friday found that the dapper open and dust and paint mist come though T/C room
Robot turn table stil error,,,, what to do???
No.2 Base pill off, testing
Door Out R/B 4th round pill off, testing
Curing Gas oven need greasing ? or modification,,,, my question before doing anything is will the system work with T/C room ???
Oven Filter change
Small Antistatic booth damper cnnect to R/C booth so Friday found that the dapper open and dust and paint mist come though T/C room
Robot turn table stil error,,,, what to do???
วันพุธที่ 13 สิงหาคม พ.ศ. 2551
Aug 14 2008
Report from TSLA that K. Suvit would not issue any letter or MOU until TCT paid for the pending amount.
Inspection of T/C room found satisfaction result on the cement work over the week end, the Gas oven entrance floor look good the water draining also look good, now wait M/T to install proper pump. There are an electrical short-circuit due to pump and computer sharing same outlet
M/T will change the power line and pump and will install Fire distinguisher one at Insp, two at T/C area
FP drop to 44%
Additional 1 hr. delay due to misunderstanding on the mount T/F
3E00 delay 13 mins. due to expansion roll adjustment off position.
669L still pulling FP down beside seeding there are lot of paint run, orange peel, on armrest
night shift have more crater and thread, need check mixing process
669L masking jig will need a week to complete, TCT will mask the parts for now but the quality is questionable, QA and Engineer will go to TKT to clean spec and will need TOYOTA decision for temporary acceptation, The masking jig we have only one set, additional caps are being order, TCT will go ahead and order base as well
Inspection of T/C room found satisfaction result on the cement work over the week end, the Gas oven entrance floor look good the water draining also look good, now wait M/T to install proper pump. There are an electrical short-circuit due to pump and computer sharing same outlet
M/T will change the power line and pump and will install Fire distinguisher one at Insp, two at T/C area
FP drop to 44%
Additional 1 hr. delay due to misunderstanding on the mount T/F
3E00 delay 13 mins. due to expansion roll adjustment off position.
669L still pulling FP down beside seeding there are lot of paint run, orange peel, on armrest
night shift have more crater and thread, need check mixing process
669L masking jig will need a week to complete, TCT will mask the parts for now but the quality is questionable, QA and Engineer will go to TKT to clean spec and will need TOYOTA decision for temporary acceptation, The masking jig we have only one set, additional caps are being order, TCT will go ahead and order base as well
วันอังคารที่ 12 สิงหาคม พ.ศ. 2551
Aug 13 2008
I order production start delay 2 hrs. due to T/C room not ready and big mess due to construction (Ties change, and cement work on on the long weekend)
Changing new compressed air filter for all paint in T/C room and change new host for paint and air guns but no paint guns hanger so I asked M/T to design and install oneright away,
There were report fro QA that there are some WISH pill off on Sat.
669L T/C FP is up unknowing on Sat.
Start proper training on 4 new engineers for Mount T/F and Sanding 1,2 FII
not really good, we will need training for trainner
669L masking jigs broke down unrepairable CB will replace the cap for us but will take time ??? what we gona do ???
Changing new compressed air filter for all paint in T/C room and change new host for paint and air guns but no paint guns hanger so I asked M/T to design and install oneright away,
There were report fro QA that there are some WISH pill off on Sat.
669L T/C FP is up unknowing on Sat.
Start proper training on 4 new engineers for Mount T/F and Sanding 1,2 FII
not really good, we will need training for trainner
669L masking jigs broke down unrepairable CB will replace the cap for us but will take time ??? what we gona do ???
สมัครสมาชิก:
บทความ (Atom)