Planing yesterday 669L Granish R parts not in as plan from suppler,
Mount 3E00 10 mins delay
X11J 10 mins delay x 2
and 669L Granish R as aboved
InspT/F 2.91% defect @ 5756 pcs. input
3E00 need to put the masking cover again due to FIlm ขาด downside is when wipping part the silver on cover spill to parts.
Oil Drip in oven leave make on hangers
Yamaha Paint run problems, some color fade in pink color...
60+% first time of this month due to very little 669L processes,
pass 2 weeks night shift F/P higher than day shift may be dur to temperature and humidity
Today current plan will end 12:00 and if 3E00 came in on time will have additional 3 hrs Working time
Party adjust Air Balance in Masking room, now + but need some precise doors control
Masking room FP 71% due to less work and worker can clean masking jigs cover every 4 time painting