วันพุธที่ 13 สิงหาคม พ.ศ. 2551

Aug 14 2008

Report from TSLA that K. Suvit would not issue any letter or MOU until TCT paid for the pending amount.


Inspection of T/C room found satisfaction result on the cement work over the week end, the Gas oven entrance floor look good the water draining also look good, now wait M/T to install proper pump. There are an electrical short-circuit due to pump and computer sharing same outlet

M/T will change the power line and pump and will install Fire distinguisher one at Insp, two at T/C area



FP drop to 44%


Additional 1 hr. delay due to misunderstanding on the mount T/F

3E00 delay 13 mins. due to expansion roll adjustment off position.



669L still pulling FP down beside seeding there are lot of paint run, orange peel, on armrest


night shift have more crater and thread, need check mixing process


669L masking jig will need a week to complete, TCT will mask the parts for now but the quality is questionable, QA and Engineer will go to TKT to clean spec and will need TOYOTA decision for temporary acceptation, The masking jig we have only one set, additional caps are being order, TCT will go ahead and order base as well