PCI Meeting:
3E00 silver flake defect on the parts are increasing and defect get bigger,
gas curing oven cleaning burner chamber and filter will test and check dust level both end of oven before and after turn on,
Paint filter mesh found in water in robot booth, PCI to set system visual control between New, Wash and scrap filter...
Robot report, that the check valve near CCV may be in bad condiion, Axis 1 and 2 on Robot 1 always error etc.
DI RO and Normal switch valve
R/C sanding dust in the back of parts: test dishwasher
1st and 2nd Axis alway error
วันอาทิตย์ที่ 31 สิงหาคม พ.ศ. 2551
วันพฤหัสบดีที่ 28 สิงหาคม พ.ศ. 2551
Aug 29 2008
Mount Day 3E00 x2 delay stop and go, Wate Temp is too high 32-33 at the begining
NIght R/C masking delay
Insp 1 5.59%(No BT) @5867 pcs. YAMAHA reject pinholes need lower dipping angle the curent angle indicator not fine enough
NIght R/C masking delay
Insp 1 5.59%(No BT) @5867 pcs. YAMAHA reject pinholes need lower dipping angle the curent angle indicator not fine enough
วันพุธที่ 27 สิงหาคม พ.ศ. 2551
Aug 28 2008
Planing yesterday 669L Granish R parts not in as plan from suppler,
Mount 3E00 10 mins delay
X11J 10 mins delay x 2
and 669L Granish R as aboved
InspT/F 2.91% defect @ 5756 pcs. input
3E00 need to put the masking cover again due to FIlm ขาด downside is when wipping part the silver on cover spill to parts.
Oil Drip in oven leave make on hangers
Yamaha Paint run problems, some color fade in pink color...
60+% first time of this month due to very little 669L processes,
pass 2 weeks night shift F/P higher than day shift may be dur to temperature and humidity
Today current plan will end 12:00 and if 3E00 came in on time will have additional 3 hrs Working time
Party adjust Air Balance in Masking room, now + but need some precise doors control
Masking room FP 71% due to less work and worker can clean masking jigs cover every 4 time painting
Mount 3E00 10 mins delay
X11J 10 mins delay x 2
and 669L Granish R as aboved
InspT/F 2.91% defect @ 5756 pcs. input
3E00 need to put the masking cover again due to FIlm ขาด downside is when wipping part the silver on cover spill to parts.
Oil Drip in oven leave make on hangers
Yamaha Paint run problems, some color fade in pink color...
60+% first time of this month due to very little 669L processes,
pass 2 weeks night shift F/P higher than day shift may be dur to temperature and humidity
Today current plan will end 12:00 and if 3E00 came in on time will have additional 3 hrs Working time
Party adjust Air Balance in Masking room, now + but need some precise doors control
Masking room FP 71% due to less work and worker can clean masking jigs cover every 4 time painting
Aug 27 2008
669L still have many problems, start using new jigs which are very heavy and the setting created much pinholes, Robots also have many problems the turntable is now nearly stop, the pump is mulfunction causing many defect
Got my Agitator order from IWATA
TKT K Pakong came to discuss 669L delivery and now we use substrate 16% scrape still can not close order
Production mount finish at 3 pm.
3E00 mold brok down today so no parts for a while
Got my Agitator order from IWATA
TKT K Pakong came to discuss 669L delivery and now we use substrate 16% scrape still can not close order
Production mount finish at 3 pm.
3E00 mold brok down today so no parts for a while
วันอาทิตย์ที่ 24 สิงหาคม พ.ศ. 2551
Aug 23 2008
To TCT mainly to talk to Justin Impac, their team have observed TCT production at night time and find out many of our know weak point such as so much talking during work, the start time of Insp 2 etc...
Production found that yesterday day shift FP not good may be due to booth efficiency drop and after end shift cleaning night shift back to normal we need better review of cleaning frequency
Production found that yesterday day shift FP not good may be due to booth efficiency drop and after end shift cleaning night shift back to normal we need better review of cleaning frequency
วันพุธที่ 20 สิงหาคม พ.ศ. 2551
Aug 21 2008
Aug 20 result
Mount total delay 1 hr. (night shift),
Insp T/F 4.92% shift B only
High Humidity in T/F room, Temp is OK
Mold for 669L 4 holes brokedown TKT send for repair ETC Friday
Many defect are related to the cleanliness of surface, it is possible that the spray washer is not effective
Mount total delay 1 hr. (night shift),
Insp T/F 4.92% shift B only
High Humidity in T/F room, Temp is OK
Mold for 669L 4 holes brokedown TKT send for repair ETC Friday
Many defect are related to the cleanliness of surface, it is possible that the spray washer is not effective
วันอังคารที่ 19 สิงหาคม พ.ศ. 2551
Aug 20 2008
Test Film Taiwan Camry design : a little too dark, othewise look ok, the PVA difficult to wash off
Removed Plastic cover on the new booth T/C room to reinstate the air balance
This morning start T/F Yamaha for Suncolor
669L Arerest 4 holds deformation problems: TKT testinjection with add weight to the 4 holes part causing the one hole to be NG,still no clear direction
วันจันทร์ที่ 18 สิงหาคม พ.ศ. 2551
Aug 18 2008
Install LCD monitor in meeting room FII, First time using HDMI cable connecting from DVI port on the computer,
IMPCT Team Kick off, Factory tour and discussion
IMPCT Team Kick off, Factory tour and discussion
Aug 19 2008
Yesterday delay by T/F 45 mins. Triangular pin come lose and keep movimg out...
Major paint run problem TOYOTA day shift
R/C parts suffer needle holds
Major paint run problem TOYOTA day shift
R/C parts suffer needle holds
Mr Yor with Lutenant form Thai Air force visit SPI Khun Choto show Air Field hanger and facilities and capability
Take them to Lunch at "ภ"
Goto Novatel to meet IMPAC to sign off MOU
วันอาทิตย์ที่ 17 สิงหาคม พ.ศ. 2551
PCI Meeting Aug 18 2008
Clearing of some unused or not use often jigs to FII finish within this month
No.2 Base pill off, testing
Door Out R/B 4th round pill off, testing
Curing Gas oven need greasing ? or modification,,,, my question before doing anything is will the system work with T/C room ???
Oven Filter change
Small Antistatic booth damper cnnect to R/C booth so Friday found that the dapper open and dust and paint mist come though T/C room
Robot turn table stil error,,,, what to do???
No.2 Base pill off, testing
Door Out R/B 4th round pill off, testing
Curing Gas oven need greasing ? or modification,,,, my question before doing anything is will the system work with T/C room ???
Oven Filter change
Small Antistatic booth damper cnnect to R/C booth so Friday found that the dapper open and dust and paint mist come though T/C room
Robot turn table stil error,,,, what to do???
วันพุธที่ 13 สิงหาคม พ.ศ. 2551
Aug 14 2008
Report from TSLA that K. Suvit would not issue any letter or MOU until TCT paid for the pending amount.
Inspection of T/C room found satisfaction result on the cement work over the week end, the Gas oven entrance floor look good the water draining also look good, now wait M/T to install proper pump. There are an electrical short-circuit due to pump and computer sharing same outlet
M/T will change the power line and pump and will install Fire distinguisher one at Insp, two at T/C area
FP drop to 44%
Additional 1 hr. delay due to misunderstanding on the mount T/F
3E00 delay 13 mins. due to expansion roll adjustment off position.
669L still pulling FP down beside seeding there are lot of paint run, orange peel, on armrest
night shift have more crater and thread, need check mixing process
669L masking jig will need a week to complete, TCT will mask the parts for now but the quality is questionable, QA and Engineer will go to TKT to clean spec and will need TOYOTA decision for temporary acceptation, The masking jig we have only one set, additional caps are being order, TCT will go ahead and order base as well
Inspection of T/C room found satisfaction result on the cement work over the week end, the Gas oven entrance floor look good the water draining also look good, now wait M/T to install proper pump. There are an electrical short-circuit due to pump and computer sharing same outlet
M/T will change the power line and pump and will install Fire distinguisher one at Insp, two at T/C area
FP drop to 44%
Additional 1 hr. delay due to misunderstanding on the mount T/F
3E00 delay 13 mins. due to expansion roll adjustment off position.
669L still pulling FP down beside seeding there are lot of paint run, orange peel, on armrest
night shift have more crater and thread, need check mixing process
669L masking jig will need a week to complete, TCT will mask the parts for now but the quality is questionable, QA and Engineer will go to TKT to clean spec and will need TOYOTA decision for temporary acceptation, The masking jig we have only one set, additional caps are being order, TCT will go ahead and order base as well
วันอังคารที่ 12 สิงหาคม พ.ศ. 2551
Aug 13 2008
I order production start delay 2 hrs. due to T/C room not ready and big mess due to construction (Ties change, and cement work on on the long weekend)
Changing new compressed air filter for all paint in T/C room and change new host for paint and air guns but no paint guns hanger so I asked M/T to design and install oneright away,
There were report fro QA that there are some WISH pill off on Sat.
669L T/C FP is up unknowing on Sat.
Start proper training on 4 new engineers for Mount T/F and Sanding 1,2 FII
not really good, we will need training for trainner
669L masking jigs broke down unrepairable CB will replace the cap for us but will take time ??? what we gona do ???
Changing new compressed air filter for all paint in T/C room and change new host for paint and air guns but no paint guns hanger so I asked M/T to design and install oneright away,
There were report fro QA that there are some WISH pill off on Sat.
669L T/C FP is up unknowing on Sat.
Start proper training on 4 new engineers for Mount T/F and Sanding 1,2 FII
not really good, we will need training for trainner
669L masking jigs broke down unrepairable CB will replace the cap for us but will take time ??? what we gona do ???